Construction Updates


Construction Notices


Posts

  • November 18th Update

    The contractor completed paving last week Thursday November 12th. They will continue to work on grading and restoration in various areas around the village before they wrap up for the year. They are expected to be finished with their work this week and will pick up in the spring next year to complete the project. Final completion for the project is expected in June 2021. Here are some photos of their work over the last week.

  • November 9th Update

    The contractor, Mead Bros., will be paving W Chestnut, S Summit, S Clark, Oak, W Walnut, and S Main Streets starting on Thursday November 12th. Both base and top courses will be paved on the same day. The contractor will start preparing gravel and subgrade in these areas early this week. Please be aware of temporary road closures in these areas. Only emergency vehicles will be allowed to access areas closed until pavement has sufficiently cooled for traffic. We ask residents to not access roads blocked by barriers and barrels to prevent damage to newly placed pavement until construction worker remove the barriers. We appreciate your understanding in this matter.

    As construction season comes to an end, the contractor plans to wrap up construction in the next couple of weeks. Construction will resume next spring when weather permits to finish the remainder of the project. Final project completion is expected in June 2021.

    Check out some photos of the contractor’s work from last week.

  • November 3rd Update

    The contractor is continuing their work along S Summit Street. They have removed some sidewalk and driveways in areas where storm drain pipe is being installed. They will prepare and form sidewalks and driveways for concrete beginning today. Here are a few photos of their most recent work.

  • October 23rd Update

    The contractor is working on installing pipe along S Summit Street. They will continue to work their way to the north along S Summit Street over the next several days and will conclude their work in this area just north of Chestnut Street. Here are some photos of their work.

  • October 12th Udate

    Last week the contractor worked on grading and seeding along S. Main, Oak, and Clark Streets. They will continue to work on grading and seeding in various areas around Webberville. Here are a few pictures of their work last week.

  • Paving Completed September 29th

    The contractor wrapped up paving the top course on Maple, Chestnut, Walnut, Oak, and S Howard streets. Below are some photos of their work. They will continue to install storm pipe on S Main Street and perform restoration work in previous work areas.

  • Paving Expected to begin on September 22nd

    The contractor is expected to begin paving Franklin, East Chestnut, Summit, South Clark, Oak, Maple, East and West Walnut, South Howard, Monroe and Gramer Road on September 22nd. They are currently preparing these areas with sub grade gravel placement, grading, and structure raising. These areas will be closed to all traffic except for emergency vehicles during paving. Signage and flag persons will advise on alternate routes for vehicles during this time.